I follow the construction. One reason why the pace dropped was the short term goal of closing the underground parking lot. They threw a ridiculous amont of workers there to finish it ( multi-storey-underground parking). And indeed .. they already are nearing the full closure of the parking lot and it already looks level with the outer space of the camp nou. I think once that goal is achieved many workers will be reassigned to other parts of the stadium (and diamonds) and the pace will accelerate again.
 

Windhook

Well-known member
I follow the construction. One reason why the pace dropped was the short term goal of closing the underground parking lot. They threw a ridiculous amont of workers there to finish it ( multi-storey-underground parking). And indeed .. they already are nearing the full closure of the parking lot and it already looks level with the outer space of the camp nou. I think once that goal is achieved many workers will be reassigned to other parts of the stadium (and diamonds) and the pace will accelerate again.
Could be it and I've noticed it as well, but work on third tier has been going on as well. Something unnecessary if we really focused on returning to Camp Nou in Laporta's promised schedule.
 

Total-Football

Senior Member
Could be it and I've noticed it as well, but work on third tier has been going on as well. Something unnecessary if we really focused on returning to Camp Nou in Laporta's promised schedule.
Im pretty positive the main focus is to close the parking lot because that area is the most concentrated in terms of workers. I read somewhere that phase 2 (45k) requires that hence the full focus.
 

Total-Football

Senior Member
Four milestones soon (matter of weeks)
1 closing up of the parking lot
2 third and final cantilever fully concreted
3 almost all metal structure in place (except roof and roof supports)
4 All pillars concreted

I see those 4 achieved by 31 12 December at most.. I always watch daily vlogs with my coffee when I wake up.

Things that will take place still for months :
1- placement of third stand pieces
2- placement of ceramic plates (currently they are installing their supports in the first cantilever, and it's work actually)
3- construction of vip rooms (currently concreting the floors that will separate first vip level from second level)
4- construction inside the five diamonds ( all now have been built and concreted in terms of external shape)

Still a lot more of details but this is in a nutshell.
 